Aligned RJ-01 Data Center

Rodovia Presidente Dutra, 4.648, Jardim José Bonifácio, São João de Meriti, RJ 25565-350, Brazil

OperationalAligned Data CentersSão João de MeritiAligned Data Centers site

  • Wholesale
  • Verified November 2026
  • 2 compliance reports

About Aligned RJ-01

Aligned RJ-01 is a wholesale data center operated by Aligned Data Centers in São João de Meriti. It's one of 1 facilities we track in the São João de Meriti market, a tier 3 market.

UPS redundancy is 1.33 MW UPS line-ups; N+1 block redundant and generators are 2,500 kW backup generators. Cooling is Minimum N+1; closed-loop chilled water.

Former ODATA site. ODATA lists 20,000 m² (about 215,278 sq ft) for this site without saying whether that is building or land area.

  • Industry leaders, not a call centerOur team brings 20 to 30 years from major data center platforms, the channel and data center brokerage.
  • Pricing in days, not weeksOne request reaches the providers that fit. No chasing reps one by one.
  • We negotiate, you signWe know what buyers in this market pay and use it to get you better terms.

Aligned RJ-01 key details

Building size
Not published
Colocation space
Not published
Total power
Not published
Critical IT power
Not published
Availability
Not published
Type
Wholesale
Specs checked
November 2026

Buyer note: Aligned Data Centers does not publish critical IT power, available capacity, power density per rack and carrier count for Aligned RJ-01. That is common, and it is exactly what to ask for in writing with your quote. We confirm these figures with the provider before you sign.

Aligned RJ-01 compliance

Aligned Data Centers reports these certifications and attestations for Aligned RJ-01. Ask for current reports during your evaluation.

ISO 27001PCI DSS

Aligned RJ-01 location

Address
Rodovia Presidente Dutra, 4.648, Jardim José Bonifácio, São João de Meriti, RJ 25565-350, Brazil

Aligned RJ-01 specifications

Checked against Aligned Data Centers’s website in November 2026. Where the provider’s own sources disagreed, we left the figure out rather than guess. Providers update specs on their own schedule, so we confirm the current numbers with them before you sign.

Power

UPS redundancy1.33 MW UPS line-ups; N+1 block redundant
Generator redundancy2,500 kW backup generators

Cooling

Cooling redundancyMinimum N+1; closed-loop chilled water

Security

Fire suppressionDual interlocking pre-action zoned fire protection; VESDA early smoke detection

Building

Facility typeHyperscale
Tier designDesigned to Tier III standard

Is Aligned RJ-01 the right fit?

Our read from the published specs, plus what we'd tell you from the inside. We confirm the details with Aligned Data Centers before you commit.

Where it fits

  • Larger deployments, typically hundreds of kW and up, sold as halls, suites or dedicated space
  • Regulated workloads that need ISO 27001 and PCI DSS

Insider advice

  • Get usable kW per cabinet in writing. Providers quote breaker size, and a 30A 208V circuit delivers about 5 kW under the 80% rule.
  • Ask about priority fuel delivery contracts, not just tank size. In a regional outage, the sites with priority contracts get fuel first.
  • An SLA credit is a slice of one month's bill. It won't cover your lost revenue, so judge the facility on its incident history, not its credit schedule.
  • Visit day and night. Check lighting, parking and nearby rail, chemical plants, gas lines and flight paths.

Explore