GPU colocation is the practice of buying your own GPU servers and placing them in a third-party data center that supplies the space, power, cooling and network. For an enterprise AI proof of concept of one to eight systems, most enterprise data centers can host it. The questions that decide cost are rack density, deployment labor and connectivity.
That is the short version. The long version involves a 300-pound server, a circuit breaker with opinions and a finance team asking why the "small pilot" needs four racks.
Here is what we see in buyer requests on this directory. More enterprises are buying colocation for internal AI projects. Not cloud providers, neoclouds or AI companies. Regular businesses, many of them mid-market. Instead of renting GPUs by the hour from a hyperscaler or a GPU cloud, they buy the hardware outright, often B200 or B300 class systems from NVIDIA DGX or Supermicro, and they need somewhere to plug it in.
This guide covers what those deployments draw, what a data center needs to say yes, the one-rack-or-two decision and the costs that show up after the hardware invoice. For density limits, see the high density colocation guide. For quote math, see the colocation pricing guide.
| First deployment | System power (DGX B200 at about 14.3 kW max each) | Racks at one system per rack | Racks at two per rack | What the data center has to say yes to |
|---|---|---|---|---|
| 1 system | about 14.3 kW | 1 | 1 | A single higher-power rack. Most enterprise facilities can do this |
| 4 systems | about 57 kW | 4 | 2 | A small high-power row. Usually manageable |
| 8 systems | about 114 kW | 8 | 4 | Real planning on circuits and cooling, but within reach for many sites |
| 15 systems | about 215 kW | 15 | 8 | A dedicated zone, careful airflow design and a serious power conversation |
| 32 systems | about 458 kW | 32 | 16 | This is where power and cooling start to worry the operator |
System power only. Add switches, storage and management gear. Supermicro HGX systems and DGX B300 land in a similar range per system, covered below.
Why are enterprises choosing GPU colocation over renting?
Renting GPUs is a great way to start and an expensive way to stay. Once a team has a workload it runs every day, the meter starts to feel personal. Owning the hardware turns an open-ended hourly bill into a purchase plus a predictable monthly colocation charge.
Other reasons we hear: control of data and models, guaranteed access to GPUs rather than whatever a cloud has free this week and a chance to learn AI infrastructure before a bigger build.
What they do not want is to put a 14 kW server in the office server room. That room was designed for a few file servers and a router, and it has been running on optimism since 2011. Plugging a GPU system into it is how you find out where the building's breakers are.
So GPU colocation becomes the middle path. The enterprise owns the gear. A data center supplies the power, cooling, security and carrier access that an office never will.
We are excited about this trend, and not only because it fills a directory. A lot of small and mid-market businesses can do a great deal with the right infrastructure. They are creative, they move fast and they turn an idea into a go-to-market test in weeks instead of quarters. A few owned GPU systems in a good facility give them room to try things without asking a cloud bill for permission.
What does a first enterprise AI deployment look like?
Smaller than the headlines suggest. In the requests we see, first deployments range from a single system up to 10 to 15 systems. The most common shape is four to eight DGX or Supermicro systems.
Size depends on what the team is building:
- Inference: serving a model to internal users or customers. Load follows traffic, and a few systems can go a long way.
- Training or fine-tuning: teaching a model on company data. Training jobs tend to keep GPUs near full power for long stretches, and multi-system training needs a fast network between the boxes.
- Both: the usual answer by month three.
That last point matters for the contract. A POC that starts as inference on two systems often wants eight systems for training by the time the paperwork is signed. Ask for room to grow before you need it.
How much power does a GPU server really draw?
More than anything else your IT team has racked. These are the published figures from the hardware makers' own documents.
NVIDIA DGX B200
The NVIDIA DGX B200 user guide lists 14.3 kW maximum system power, a 10U chassis, six 3.3 kW power supplies, a maximum weight of 313.9 pounds and airflow of 1,550 CFM. Heat output is listed at 48,794 BTU per hour, which is roughly four tons of cooling for one box.
NVIDIA DGX B300
The NVIDIA DGX B300 user guide lists power consumption of 14.5 kW, a 15 kW system maximum and 10 rack units. It comes in two versions. The power supply version has twelve 3.2 kW supplies on 200 to 240 volt AC. The busbar version runs on 54 volt DC from a rack busbar. If you ordered the busbar version, the data center needs a rack built for it, so confirm which one is on the purchase order before you pick a facility. The power supply version weighs about 370 pounds.
Supermicro HGX B200 systems
Supermicro builds 8-GPU systems on the NVIDIA HGX B200 board. Its spec page for one 10U air-cooled model lists six 5,250 W supplies in a 3+3 redundant layout, which means up to about 15.75 kW of supply capacity on each side. That is a supply rating, not a measured draw, and Supermicro does not publish a single maximum draw figure on that page. Ask your reseller for the configured power estimate and plan to it.
The practical rule: budget about 14 to 15 kW per 8-GPU system at full load, then add networking and storage. Your quote should be built on that number, not on the nameplate of whatever rack you happen to rent.
Can an enterprise data center handle GPU colocation?
Good news first. Most enterprise data centers can handle a four to eight system deployment. That is roughly 57 to 115 kW of system load. It is real power, but it is not an AI campus.
The concern starts around 32 systems. At about 14.3 kW each, that is roughly 458 kW before networking. A facility built in the 2000s for 5 to 10 kW racks may have the floor space but not the power distribution or cooling headroom to put that much load in one area. The operator now has to plan rather than simply sell a row.
Cooling is usually the tighter limit. A two-system rack makes about 97,600 BTU per hour of heat, or about eight tons of cooling, in one footprint. The DGX systems above are air-cooled, and air has a ceiling. Many halls built for standard enterprise workloads were designed long before anyone asked them to cool 30 kW in one rack. Our data center cooling guide explains where air runs out and why.
Do not take a facility's word for it in a sentence. Ask for the per-rack density they will contract to, the cooling method in the specific hall and whether they have hosted this class of system before.
Should you run one GPU system per rack or two?
This is the decision that moves your bill the most, and it gets the least attention. The two common answers are 15 to 17 kW per rack, which fits one system, or 30 to 40 kW per rack, which fits two.
One system per rack at 15 to 17 kW
A single 14.3 kW system plus a top-of-rack switch fits in this band. It is the easier ask for most facilities. One 208V, 60A three-phase circuit has a nameplate of about 21.6 kW, or about 17.3 kW at the common 80% continuous load rule, with a matching circuit on the B side for redundancy. That is close to a natural fit for one system.
The downside is sprawl. Eight systems means eight racks.
Two systems per rack at 30 to 40 kW
Two 10U systems use 20U, which leaves room in a standard rack for switching and patching. The load is about 29 kW from the two systems alone, so you need a facility that will contract to 30 to 40 kW per rack. Fewer facilities say yes, and the ones that do will want to talk about airflow, containment and power distribution in detail.
The GPU colocation math on rack count
Fewer racks mean fewer one-time charges and less material. Every rack needs its own power whips, receptacles, containment panels, cabling and floor space. Install and setup fees (NRCs) are often tied to the number of racks or circuits.
| Item | 8 systems at one per rack | 8 systems at two per rack |
|---|---|---|
| Racks | 8 | 4 |
| Power whips and receptacles | 8 racks' worth, A and B | 4 racks' worth, A and B, at higher capacity |
| Containment and floor space | 8 positions | 4 positions |
| Per-rack setup NRCs | 8 times | 4 times |
| Facilities that can host it | More | Fewer |
Neither answer is always right. Two per rack cuts the one-time bill and the footprint. One per rack widens your choice of facilities and may get you a better price per kW. Get both versions quoted and compare total cost over the term.
Who handles rack and stack, cabling and configuration?
Ask this before you buy the hardware, not after it is sitting on a loading dock.
An 8-GPU system weighs about 290 to 370 pounds. Someone has to receive it, unbox it, lift it into the rack, cable power and network, label every cable and then get the system configured and talking to your network. Multiply that by eight and add a network fabric if you plan to train across systems.
Ask the facility three things:
- Do you offer rack and stack, cabling and labeling as a service?
- If not, do you have a preferred vendor who works in your building regularly?
- Who configures the systems after they are racked, and who owns the network setup?
Deployment labor, cabling, optics and configuration can get expensive quickly, sometimes enough to make a team rethink the hardware purchase itself. A cheap rack in a facility that has never seen a GPU server can cost more than a fair rack in one that installs them every month.
The good news is that some providers are easy to work with and do this regularly. They have a receiving process for heavy gear and staff who have racked these systems before. Our get quotes page can match you with facilities that already host GPU deployments.
What does GPU colocation cost?
Think in five parts: NRCs, MRCs, term, price per kW and support.
NRCs and MRCs
NRCs are one-time charges: setup, power installation, containment, cabling and any deployment services. MRCs are monthly recurring charges: the space and power commitment, cross connects, bandwidth and any bundled support.
For GPU deployments the NRC line runs larger than most buyers expect, because the power work is larger. Get it itemized.
Price per kW and term
In current retail quotes, we see all-in colocation pricing of about $215 to $280 per kW per month. Applied to eight DGX B200 systems at about 114 kW, that range works out to roughly $24,600 to $32,000 a month for space and power alone. Treat that as an illustration. High-power deployments are often quoted differently, and your price depends on market, facility and density. Our colocation pricing guide shows how to convert any quote to dollars per usable kW.
Term matters too. A three-year term on a one-year experiment is how a POC becomes a lease. Ask about shorter terms, expansion rights and what happens if the project ends early. The colocation agreement guide covers early termination and renewal language.
Support, especially out of state
If the facility is not near your team, remote hands become your hands. In current quotes, we see remote hands at about $100 to $250 per hour, billed hourly or as bundled hours, and some smaller providers include it with select colocation services. A GPU system that needs a reseat or a drive swap at 2 a.m. will remind you why that line matters. Ask what technicians are allowed to touch on GPU hardware, how fast they respond and how billing works after hours.
Network connectivity
AI work moves a lot of data. Training data has to get in, and results or inference traffic have to get out. Ask which carriers are in the building, what bandwidth is available and what cross connects cost. In current quotes, we see cross connects at about $100 to $450 per month each. A deployment that needs several of them can change the real cost per kW more than a small difference in the power rate.
How do you choose a GPU colocation provider?
Start with the hardware, not the brochure. Know your model, power version, count and growth plan.
- Density in writing. The per-rack kW they will contract to, in the hall you will occupy.
- Cooling fit. Whether that hall can remove about 14 to 29 kW of heat per rack with air, and what happens above that.
- Experience. Whether they host 8-GPU systems today and can describe how.
- Deployment help. In-house rack and stack or a preferred vendor, with prices.
- Support model. Remote hands rates, response times and after-hours rules.
- Network. Carriers on site, bandwidth options and cross connect pricing.
- Room to grow. Contiguous space and power for the next phase.
Smaller and mid-sized operators are often more flexible on all of this. Larger providers tend to stick to standard offers. Neither is automatically better, so compare both.
GPU colocation buyer checklist
Bring this list to every facility conversation:
- System model, count and power version (PSU or busbar for DGX B300)
- Planned kW per rack: 15 to 17 kW for one system or 30 to 40 kW for two
- Total kW now and in 12 months
- Circuit type, voltage and amperage per rack, A and B
- Cooling method in the specific hall
- Floor loading for racks with two 300-plus-pound systems
- Itemized NRCs for power, containment and setup
- MRCs, price per kW and any minimum commitment
- Term length, expansion rights and early termination terms
- Rack and stack, cabling, labeling and configuration: who does it and what it costs
- Remote hands rates, response time and after-hours billing
- Carriers, bandwidth and cross connect pricing
- Receiving process for heavy freight
Frequently asked questions about GPU colocation
What is GPU colocation?
GPU colocation means you own the GPU servers and a third-party data center hosts them. The facility supplies space, power, cooling, security and network access. You manage the hardware and software, or pay for help.
How much power does a DGX B200 use?
NVIDIA lists the DGX B200 at about 14.3 kW maximum. The DGX B300 is listed at 14.5 kW with a 15 kW system maximum. Plan about 14 to 15 kW per 8-GPU system, plus networking and storage.
Can a standard data center host GPU colocation?
For a small deployment, usually yes. Most enterprise data centers can host four to eight systems. Around 32 systems, power and cooling become a real planning problem for the operator.
Is GPU colocation cheaper than renting GPUs in the cloud?
It depends on use. Hardware that runs most of the day for years can cost less to own and colocate. Short or bursty work often fits renting better. Model both over your expected term.
How many GPU systems fit in one rack?
Usually one or two 10U systems. One system needs about 15 to 17 kW per rack. Two need about 30 to 40 kW, which fewer facilities can support.
What should I ask before signing for GPU colocation?
Ask about contracted rack density, cooling method, deployment services, remote hands rates, carriers and cross connect pricing. Then ask about term, expansion rights and every NRC.
Where to go from here
Write down your hardware, count and growth plan, then get quotes for both rack layouts. Our get quotes page can connect you with facilities that host GPU deployments regularly. For hardware power and environmental specs, go to the source: the NVIDIA DGX B200 user guide and the NVIDIA DGX B300 user guide.
This article is general information, not legal, financial or engineering advice. Prices and capabilities vary by market, facility and deal. Confirm all terms in a written quote.
More in GPU and AI Colocation Articles and Guides
Compare facilities: High-density data centers
Comparing data centers?
Send us your requirements. We'll shortlist the providers that fit and get you pricing.