What Neoclouds Need to Know About Buying Wholesale Colocation

Wholesale colocation for neoclouds. Why capacity and credit come before rate, the terms and timelines to expect, and what to ask before you sign.

12 min read

Last verified November 23, 2026

Wholesale colocation for a neocloud is a capacity and credit problem first, and a rate problem second. Vacancy is near 1% and most new halls are already spoken for. Buyers with a realistic timeline, a short operator list and a term they can honor get further than buyers who spray a hundred RFIs hoping something is live in six months.

Look, we get it. Your own customer wants GPUs turned up in a quarter. The market has other plans. As of November 2026, the capacity figures below come from CBRE's H1 2026 report (published August 27, 2026) and JLL's Midyear 2026 report (published August 11, 2026). The term lengths in the table are not an index. They are what buyers commonly see at each scale.

Deal size Term buyers commonly see Timeline the market can usually support What it means in practice
About 1 to 5 MW 5 to 7 years A ready hall, if you can find one A five-year term still shows up, but the best rooms go first
About 10 MW 7 to 10 years Often a 2027 or 2028 delivery You are preleasing, not shopping leftover space
20 MW and up 10 to 15 years Build-to-suit work that can start years before opening Fifteen-year terms are common once the operator is building for you
100 MW class The operator sets the term A multi-year, phased delivery You are not really negotiating term. You are deciding whether to take the hall

Why is capacity the real constraint in wholesale colocation?

Every serious wholesale colocation search starts with the same question. Do you have the megawatts, or do you know who does? What is available is often not what the buyer wants, and what the buyer wants is often not available yet.

JLL's North America Data Center Report Midyear 2026 puts vacancy at 1% for a third straight year and says available capacity is limited to small, fragmented blocks. Most tenants securing space today, JLL says, are contracting for 2028 deliveries. CBRE's North America Data Center Trends H1 2026 report says commitments cover 80.4% of under-construction capacity in its primary markets, up from 74.3% a year earlier. Less than 1,500 MW of future capacity remains available, or about six months of demand. JLL also counts 66 GW under construction across North America, 95% of it pre-committed.

What has made the hunt messier is a wave of warehouse and industrial retrofits marketed as ready data centers. Buyers commonly run into capacity that is not energized, a timeline that would not survive a site walk or a rendering with a megawatt number on it. A signed utility agreement beats a pretty picture. Our neocloud colocation guide walks through how to spot paper capacity.

The capacity is out there. Finding it takes a short list of operators who can prove power, cooling and a ready-for-service date, not a spreadsheet of every building in the country.

How long are wholesale colocation terms right now?

The five-year term is not dead, but it is more of a smaller-scale play than it used to be. For wholesale colocation deals in the one to five megawatt range, buyers commonly still see five to seven years. Around ten megawatts, seven to ten years is the usual conversation. At twenty megawatts and above, fifteen-year terms are becoming common. At the hundred-megawatt level, you are usually accepting the term, not shaping it.

Those bands are practitioner patterns, not a published rate card. CBRE's Phoenix chapter puts the average lease term in that one market at seven years.

This is a supply equation. Operators with real capacity in the right markets have the upper hand, and they use it. If you want a longer runway and want to lock pricing before the next round of increases, a longer term can be a reasonable position for a well-capitalized neocloud. JLL says most leases signed today carry annual escalations of 3% or more and come with no concessions. It also says rents for comparable product are up 70% on average since 2020. If your model needs flexibility, expect to pay for it or watch the best capacity go to someone who will sign longer.

Why do deployment timelines rarely match the customer deal?

This is where a lot of wholesale colocation deals start to grind. A neocloud lands a customer and now has to perform. The pressure to turn up capacity in three to six months is intense. The market rarely has that much ready power sitting around, and the operators who do are picky about who they put in the room.

Almost none of the pipeline is speculative. JLL says 95% of North American capacity under construction is already pre-committed. CBRE puts preleasing in its primary markets at 80.4%. The urgent demand lives in the window where supply is tightest. CBRE's Atlanta chapter says turnkey facilities are preleasing about 12 months before completion, and build-to-suit projects about two and a half years before completion. Fit-out is not instant either. CBRE notes that ready-for-service dates are stretching from weeks to several months as density rises, and that converting an air-cooled hall to liquid cooling can take more than six months. Our liquid cooling in colocation guide covers what that conversion involves.

If your board still has a mid-year go-live and the hall is a 2028 delivery, that is not a scheduling typo. That is the market. Build a buffer into the customer contract, or do not sign the customer contract yet.

Why does a 100-operator RFI fail in wholesale colocation?

Some neocloud teams send a request for information to fifty or a hundred operators to keep a book of options. The logic is easy to like and hard to run. Capacity gets spoken for. Pre-leases get signed. By the time you circle back to confirm a room, the answer has changed. A vendor book of that size is hard for most teams to keep current, and the noise wears out the operators you want to work with.

A hundred RFIs is not a pipeline. It is a way to train a hundred sales teams to stop taking your calls.

A short list that you refresh as you go beats a sprawling contact sheet. Confirm availability in real time, ask for utility proof and a contractual ready-for-service date, and drop anyone who cannot produce them. Our RFI vs. RFQ vs. RFP guide covers when an RFI is useful and when you should skip ahead to a tighter RFQ or RFP. If you want help narrowing the field, you can also get quotes.

When do secondary markets work for a neocloud?

Neocloud and AI infrastructure buyers have become more willing to look at secondary and frontier markets than they were a couple of years ago. The usual driver is power, both the cost and the fact that it is available. JLL says 77% of North American capacity under construction is going up in frontier markets. West Texas has been the largest beneficiary. Ohio, Louisiana, Indiana and the Carolinas have also taken a sizable share. CBRE expects West Texas to be one of the top five colocation markets in North America by 2028.

Power cost is real, but it is easy to oversimplify. The U.S. Energy Information Administration's Electric Power Annual for 2025, released October 21, 2026, puts average industrial retail rates at 6.35 cents per kWh in Texas, 9.49 cents in Virginia and 20.96 cents in California. Those are statewide industrial averages rather than colocation quotes. They also leave out demand charges, wholesale contracts and the markup inside a colo bill. Use them as a spread, not as your unit price. Then look at total contract value, including state and local incentives. A cheap kilowatt in a thin network market can still be an expensive mistake.

The factors that still matter in every market are carrier presence and network density. At this scale you want large global ISPs and more than one carrier path. A thin carrier ecosystem is a problem waiting to happen, especially for latency-sensitive work or anything that needs diverse routing. Carrier neutrality is a baseline. You should be able to contract with the carriers you want, not get funneled through a single pipe.

How should you judge a purpose-built hall versus a retrofit?

There is a real difference between a purpose-built, fault-tolerant data center and a warehouse that has been asked to become one. Buyers at larger scale are paying more attention, in part because some have already had a painful experience with a site that looked fine on paper.

Custom dedicated halls for a single tenant are a common preference at the larger end of the market. Dedicated power and systems that are not shared with a neighbor are operationally significant. If you are running inference at scale, the last thing you need is someone else's power event showing up as your cooling problem.

Ask operators about their design basis, generator configuration, cooling approach and utility relationships. Ask how power reaches the rack, what happens if a feed is lost and who owns the liquid loop if you need one. When you find a purpose-built site with a clean operating history and documents to match, pay attention. For the hardware and density side of that conversation, see our neocloud colocation guide.

How do credit and underwriting change a wholesale colocation deal?

Operators with the best capacity are being selective. CBRE says data center owners are prioritizing tenants with strong credit profiles. JLL notes that top-tier credit hyperscalers still get the most efficient construction-loan pricing, while non-credit tenant deals are judged case by case on the tenant's profile, credit support from the off-taker and location. Spreads are often 200 to 300 basis points wider than investment-grade construction loans.

Investment-grade backing matters in that setting. So does the ability to put money up. Buyers commonly hear about several months of rent paid in advance, a security deposit or a letter of credit. The teams that can show that kind of posture tend to move up the list. That is not surprising on a fifteen-year lease at ten megawatts or more. The operator is making a long bet and wants a counterparty who can perform.

If your neocloud is earlier in its capital formation, go into that conversation prepared. Know your funding story, your investors and your customer commitments. Operators are not only scoring the technical fit. They are scoring how likely you are to honor the term. The mechanics of guarantees, letters of credit and customer-contract backing are covered in our neocloud colocation post.

What sets wholesale colocation rates?

The honest answer is that the rate is a function of megawatts, market, term, timing and how much the operator wants the deal. There is no single index and no standard rate card that applies across wholesale colocation right now. Asking rates have kept rising in the latest CBRE report, and JLL's escalator language is the one to model: 3% or more a year, with no concessions. Our data center market outlook post walks through the current rent and vacancy figures.

Buyers who arrive with clear requirements, a timeline the market can meet and financials an operator can underwrite get better outcomes than buyers who treat this as a pure price negotiation. You are not just buying power and space. You are buying reliability, support and the team that has to keep the hall running.

What questions should you ask before a wholesale colocation signing?

  1. Is this capacity energized today, and if not, what is the utility-committed date for each phase?
  2. Can you show a signed electric service agreement or a utility letter for this megawatt amount?
  3. What is the contractual ready-for-service date, and what remedies apply if you miss it?
  4. What term is required at this size, and what does a shorter term cost if it is even offered?
  5. Is the hall purpose-built or a retrofit, and do I get a dedicated hall with dedicated power?
  6. How is power delivered to the rack, and is liquid cooling available now or only after a conversion?
  7. Which carriers are in the building, and can I contract with them directly?
  8. What deposit, prepaid rent or letter of credit do you require? Will any of it step down after on-time payment?
  9. When does billing start relative to the ready-for-service date, and is there a take-or-pay floor on the committed power?
  10. What happens to the contract if we are acquired or need to assign it to an affiliate with equal or better credit?

CBRE says take-or-pay floors of 60% to 85% of allocated power are becoming more common, so question 9 is not a nicety. It is part of the monthly bill.

What belongs on a wholesale colocation buying checklist?

  • Requirement written in MW and kW per rack, with a ramp that matches hardware deliveries
  • Go-live date tested against 2027 and 2028 deliveries, not a 90-day hope
  • Short operator list, not a 50-to-100 name RFI blast
  • Utility proof, energization status and a contractual ready-for-service date for each phase
  • Purpose-built versus retrofit review, plus a dedicated-hall discussion at larger scale
  • Carrier list, diversity of paths and confirmation you can contract directly
  • Cooling method confirmed, including who owns any liquid loop (liquid cooling guide)
  • Term, escalator, take-or-pay floor and billing-start language modeled over the full term
  • Credit package ready: financials, investor backing, customer contracts and any deposit or letter of credit
  • Assignment and change-of-control language reviewed before signing
  • Quotes compared on total term cost, not the first-year rate (get quotes)

For a sense of who is buying this capacity as a tenant, see our top neocloud companies list.

Frequently asked questions about wholesale colocation

What is wholesale colocation?

Wholesale colocation is a larger, usually multi-megawatt, lease of data center power and space, often in a dedicated hall or a large block of a hall. The term is longer than a typical retail cabinet deal, the credit review is heavier and you are often preleasing capacity that is still being built.

How long is a typical wholesale colocation term?

It depends on size. Buyers commonly see five to seven years in the one to five megawatt range, seven to ten years around ten megawatts and ten to fifteen years at twenty megawatts and above. CBRE's Phoenix chapter puts the average lease term in that one market at seven years. There is no national schedule by deal size.

Can a neocloud still get a five-year term?

Sometimes, usually at smaller scale. A five-year term is still something buyers see on some one to five megawatt deals. Once the operator is building a hall for you, expect the term to stretch. If you need a shorter term at larger scale, ask what it costs. Be ready to hear that the best capacity is reserved for longer commitments.

Why do operators underwrite neocloud tenants?

Because the operator is often financing a build against your contract. CBRE says owners are prioritizing tenants with strong credit profiles. If you are unrated or early in a capital raise, expect questions about investors, customer contracts, deposits and guarantees. That screening is how operators decide who gets the hall.

How many operators should get your RFI?

Far fewer than fifty or a hundred. A short list you can keep current works better in a market where rooms get preleased while a long RFI is still circulating. Start with operators who can prove power in the markets you will accept, then tighten to an RFQ or RFP once the requirement is firm.

Is a warehouse retrofit a problem for GPU workloads?

It can be. Some retrofits are done well and some are a rendering with a power number attached. High-density GPU racks are unforgiving about floor loading, cooling and how power reaches the cabinet. Ask for design documents, utility proof and a site walk. If the story only works on a slide, keep walking.

Engage early, keep the operator list short, expect a longer term at meaningful scale and come to the financial conversation prepared. When you are ready to compare a shortlist, get quotes.

More in GPU and AI Colocation Articles and Guides

Compare facilities: High-density data centers

Related

Comparing data centers?

Send us your requirements. We'll shortlist the providers that fit and get you pricing.