As of November 2026 this outlook uses CBRE North America Data Center Trends H1 2026 (published August 27, 2026) and JLL North America Data Center Report Midyear 2026 (published August 11, 2026). We refresh it each half-year when new reports come out.
The data center market is the tightest it has ever been. CBRE puts primary market vacancy at a record-low 1.4% and JLL says vacancy has held near 1% for three straight years. For colocation buyers that means fewer options, rising rents, 3% or higher annual escalators and planning a year or more ahead.
The data center market has turned into a concert ticket drop, except the tickets cost more every half-year and the venue is still under construction. This outlook explains what the latest CBRE and JLL numbers mean for your next quote, renewal or expansion.
| Metric | Latest figure | Source | What it means for buyers |
|---|---|---|---|
| Primary market vacancy | 1.4%, a record low | CBRE H1 2026 | Little existing space to choose from |
| Northern Virginia vacancy | 0.2% | CBRE H1 2026 | The biggest market is effectively full |
| North America vacancy | About 1% for a third straight year | JLL Midyear 2026 | Tightness is not a one-off |
| Preleased share of capacity under construction | 80.4% in primary markets | CBRE H1 2026 | New buildings fill before they open |
| Capacity under construction | 66 GW, 95% pre-committed | JLL Midyear 2026 | The pipeline is mostly spoken for |
| H1 2026 demand | A record 25 GW, about double a year earlier | JLL Midyear 2026 | Competition for every block |
| Rents since 2020 | Up nearly 70% | JLL Midyear 2026 | Renewals reprice sharply |
| Average rents | $337/kW/mo all-in under 250 kW; $152 to $210 plus energy (JLL's "+ E") for larger tiers | JLL Midyear 2026 | Report averages, not quotes |
| New lease escalators | Mostly 3% or more a year, no concessions | JLL Midyear 2026 | Annual increases are the norm |
| Delivery dates | Most tenants contracting for 2028 | JLL Midyear 2026 | Plan well ahead |
What does the latest data center market report actually say?
Both major reports point the same way. CBRE's North America Data Center Trends H1 2026 says primary market supply grew 33.7% year over year to a record 10,903 MW. Yet vacancy still fell to 1.4% from 1.6% a year earlier, "with new capacity absorbed as quickly as it was completed." Northern Virginia, the largest market, dropped to 0.2%.
JLL's North America Data Center Report Midyear 2026 says vacancy has stayed at 1% for the third consecutive year despite unprecedented construction. It counts 66 GW under construction, 95% of it pre-committed. JLL expects vacancy to remain near zero through 2028.
Why do the CBRE and JLL numbers look different?
They measure different things, so do not mix them in one sentence. CBRE tracks eight primary wholesale markets (Atlanta, Chicago, Dallas-Ft. Worth, Hillsboro, New York Tri-State, Northern Virginia, Phoenix and Silicon Valley) in MW. It reported 1,456.2 MW of net absorption in H1 and 7,481.1 MW under construction in those markets.
JLL covers all of North America in GW, including hyperscaler-owned capacity. Its 25 GW of H1 demand combines third-party lease signings with owner-occupied groundbreakings, which is why it dwarfs CBRE's absorption figure. JLL also defines its own market boundaries. Its Northern Virginia inventory is nearly 7 GW, while CBRE counts 4,496.5 MW. Different fences, both right.
Why are colocation prices and escalators still rising?
Simple supply and demand, with extra demand. Every data center market report this year tells the same story. CBRE reports that asking rents rose for every requirement size in H1 2026. Rates for 3 to 10 MW rose 8.3% and 500 kW to 3 MW rose 7.9%. The 250 to 500 kW tier rose 4.3%, nearly double its 2.5% increase a year earlier.
JLL says rents have increased nearly 70% since 2020, with growth averaging 9% a year. It expects that pace to hold through 2030. JLL also reports that most leases signed today carry annual escalations of 3% or more with no concessions.
What do data center market rents look like right now?
These are report averages, not quotes. They vary a lot by market, size and what the rate includes. JLL's Midyear 2026 report lists average monthly rents per kW of:
| Deployment size | JLL average rent | What it includes |
|---|---|---|
| Under 250 kW | $337 | All-in |
| 250 kW to 1 MW | $210 | Plus energy (JLL's "+ E") |
| 1 to 5 MW | $178 | Plus energy (JLL's "+ E") |
| 5 to 20 MW | $166 | Plus energy (JLL's "+ E") |
| Over 20 MW | $152 | Plus energy (JLL's "+ E") |
CBRE publishes asking rates for 250 kW and up at N+1 or Tier III design. Its H2 2025 report put the 250 to 500 kW primary market average at about $195 per kW, and H1 2026 added 4.3%, roughly $204 by our math. In Northern Virginia, CBRE says asking rates for 10-plus MW requirements rose to $160 to $185 per kW.
How does that square with our quote guide? In the retail quotes we see, all-in pricing runs about $215 to $280 per kW per month. That sits below JLL's $337 average for small deployments because the two measure different things. JLL is a research average across its markets and definitions. Our range reflects quotes buyers actually receive. Always check what a figure includes before comparing.
Translation for your budget: the free months and soft escalators of the last decade are mostly gone in this data center market. Model your total cost with the escalator compounding over the full term. Our how to read a colocation quote guide shows where escalators hide in a proposal.
Other costs are creeping in too. CBRE notes that "take or pay" minimum power floors of 60% to 85% of allocated power are becoming more common in the U.S. It also flags state large load tariffs, including a Virginia consumption tax of $0.011 per kWh that took effect July 1.
How are neoclouds and AI companies crowding the data center market?
AI demand is not just growing the pie. It is taking the biggest slices first. JLL reports that hyperscalers account for 59% of 2026 tenant demand, neoclouds 11% and pure-play AI companies 7%. CBRE says hyperscale and AI occupiers "competing for limited contiguous power blocks" drove H1 demand. The players also trade capacity with each other. JLL notes that AI companies are leasing capacity from hyperscalers while neoclouds supply capacity to hyperscalers.
For traditional enterprise buyers, the squeeze shows up in three places.
- Availability. JLL says enterprise site requirements of 500 kW to 3 MW are "struggling to secure capacity." CBRE says occupiers in Northern Virginia struggle to secure 5 to 10 MW of contiguous space. In Chicago, it expects no contiguous space of 5 MW or more to be available this year.
- Pricing. Every requirement size saw asking rate gains in H1, according to CBRE. Big AI deals set the pace and smaller tiers follow.
- Timelines. CBRE says ready-for-service fit-out dates are stretching from weeks to several months as density rises. Air-cooled halls converting to liquid cooling can take more than six months.
CBRE reports that several colocation operators in Atlanta are reserving capacity for enterprise customers to diversify their customer base. CBRE also says owners are prioritizing tenants with strong credit profiles. A stable enterprise with clean financials is a more attractive tenant than ever.
What can enterprise buyers do about AI crowding?
- Size your ask to what exists. Smaller and phased requirements fit the fragmented blocks JLL describes.
- Lead with credit. Have financials and references ready on day one. Providers are screening harder.
- Ask about enterprise allocations. Some operators are holding space for enterprise customers.
- Lock expansion rights now. A right of first refusal on adjacent space is worth more when nobody can find space.
- Plan density honestly. If you need liquid cooling later, say so now. Retrofits take months.
If you are on the neocloud side of this story, our neocloud colocation guide covers what providers ask of you.
How far ahead should you plan a colocation move?
Further than you think, because the data center market now sells space years ahead. JLL says most tenants securing space today are contracting for 2028 deliveries and that available capacity is limited to "small, fragmented blocks." CBRE reports that less than 1,500 MW of future capacity across primary markets remains available, roughly six months of demand at the current pace. In Northern Virginia, it says all capacity delivering in 2026 is already committed, pushing preleasing into 2027 and beyond.
In Atlanta, CBRE says turnkey facilities prelease about 12 months before completion and build-to-suit projects about 2.5 years ahead.
Practical planning windows based on what buyers commonly see:
- A few racks in an existing facility. Months, not years, but start before your current contract's renewal notice date.
- Hundreds of kW to a few MW. Start a year or more ahead and expect phased delivery.
- Multi-MW contiguous space. Plan for future-dated deliveries. In the tightest markets that can mean 2027 or 2028.
A structured process helps when time is tight. Our RFI, RFQ and RFP guide explains when to run an RFP and when to just request quotes.
Which data center markets still have room?
"Room" is relative in this data center market, and most of it is outside the biggest hubs. Among CBRE's eight primary markets, Chicago's 2.2% overall vacancy rate is high by primary market standards. CBRE also reports a sub-10% vacancy rate for projects delivering in Chicago by year-end 2027. Phoenix absorbed more than 260 MW of colocation space in H1 and has three new colocation projects due to complete in H2.
Most of the new room is in construction pipelines, not empty halls.
- Dallas-Ft. Worth. CBRE reports more than 765 MW under construction, 95% preleased, plus 3.7 GW of greenfield development planned. JLL says the market delivered over 2 GW in H1 while absorbing even more.
- Atlanta. Under-construction capacity rose 52.3% to 2,882 MW, now the most of any market, according to CBRE. JLL reports record absorption of 918 MW in six months.
- Austin and San Antonio. JLL says the market completed 1.7 GW and absorbed 796 MW.
- Frontier markets. JLL says 77% of capacity under construction is in frontier markets. West Texas leads, along with Ohio, Louisiana, Indiana and the Carolinas. CBRE expects West Texas to become one of the top five colocation markets in North America by 2028.
Watch out for markets that look open but are not. JLL reports that Columbus compressed to 0.1% vacancy despite new supply. CBRE notes that New York passed a moratorium on data centers larger than 50 MW in July. CBRE also publishes a chart of secondary market vacancy and rents in its report, so check the latest edition for the market you care about. Our data center tax incentives guide covers state incentives that can shift the math.
How does a tight data center market change your bargaining power?
In a tight data center market, bargaining power moves to the landlord. That does not mean you have none. It means you use it differently.
- Competition is your best tool. Get quotes from several providers on the same assumptions. Even in a tight market, providers want stable tenants.
- Speed is power. A buyer with clear requirements, a budget and a decision date often gets attention first.
- Negotiate terms, not just price. Escalator caps, expansion rights, ready-for-service dates with remedies and renewal pricing are often more valuable than a small cut in the first year's rate.
Our colocation agreement guide covers the clauses worth fighting for.
What does this mean for renewals?
Renewals are where the 70% rent increase lands. JLL says landlords are capturing substantial rent spreads on renewals, with rents for comparable product up 70% on average since 2020. If your current contract was signed in 2020 or 2021, expect a meaningful increase at renewal.
Based on what buyers commonly see, start renewal talks well before your notice deadline, ideally a year or more ahead for larger deployments. Get competing quotes even if you plan to stay put. A credible alternative is your only real bargaining power at renewal time.
When does locking a longer term make sense?
A longer term can protect you from rising market rents, but only if the contract terms are right.
It can make sense when:
- Your footprint is stable and you expect to stay put.
- You can negotiate a fixed or capped escalator that is lower than expected market rent growth. JLL expects current pricing momentum to hold through 2030.
- You can attach expansion rights and renewal options at known prices.
It may not make sense when:
- Your power density or footprint will change a lot, for example a planned move to liquid-cooled AI racks.
- The contract has uncapped escalators or pass-throughs, which erode the benefit.
- You are unsure about the site's long-term power delivery or expansion capacity.
- Early termination costs would trap you if your business changes.
CBRE reports an average lease term of seven years in Phoenix. Model the total cost under a few rent growth scenarios before you sign.
What questions should you ask providers in this data center market?
- What capacity is available now, and what is the delivery date for anything not yet built?
- Is the power for my capacity energized, and if not, when?
- What annual escalator applies, and is it fixed, capped or tied to an index?
- Are there minimum power utilization or "take or pay" requirements?
- Is this lease modified gross plus electricity or triple-net?
- Can I get a right of first refusal on adjacent space?
- What are the renewal terms and how will renewal pricing be set?
- Do you reserve any capacity for enterprise customers?
- How long will fit-out take for my density and cooling needs?
- How will new utility charges or large load tariffs pass through to me?
What belongs on a data center market planning checklist?
- Current contract renewal and notice dates on the calendar
- Power needs now and in two to three years
- Density and cooling roadmap, including any liquid cooling
- Target markets shortlisted, including secondary options
- Budget that models 3% or higher compounding escalators
- Financials and references ready for credit review
- Quotes requested from several providers on identical assumptions
- Expansion rights and ROFR requested
- Ready-for-service date and late delivery remedies in the contract
- Escalator cap and pass-through limits negotiated
- Take or pay and minimum utilization terms reviewed
- Tax incentives checked for each candidate state
- Next CBRE and JLL report dates noted for a refresh
Frequently asked questions about the data center market
What is the current data center vacancy rate?
CBRE reported 1.4% vacancy across eight primary North American markets in H1 2026, a record low, with Northern Virginia at 0.2%. JLL reported vacancy near 1% across North America for the third consecutive year.
Are data center rents still going up?
Yes. CBRE reported asking rate increases for every requirement size in H1 2026. JLL says rents are up nearly 70% since 2020 and expects current pricing momentum to hold through 2030.
How far ahead should I book colocation capacity?
For larger deployments, a year or more. JLL says most tenants securing space today are contracting for 2028 deliveries. Smaller deployments in existing facilities can move faster but still benefit from an early start.
Is AI demand making it harder for enterprises to get colocation?
Yes. JLL says enterprise requirements of 500 kW to 3 MW are struggling to secure capacity amid hyperscale and AI demand. CBRE notes some operators are reserving capacity for enterprise customers.
Should I sign a longer colocation term now?
It can make sense if your footprint is stable and you can negotiate capped escalators and expansion rights. It is riskier if your density or footprint will change significantly.
How often is this data center market outlook updated?
We plan to refresh it each half-year when CBRE and JLL publish new North America reports. Check the "As of" line at the top for the report dates behind the current figures.