Data Center Growth in 2027 and What It Means for Colocation Buyers

Data center growth in 2027 predicted. Tight capacity, pricier hardware, rising rates and moratoriums, plus what enterprises and neoclouds should plan for.

12 min read

Last verified November 25, 2026

In our view, data center growth in 2027 will be held back by power, permits and the price of money, not by a lack of demand. Vacancy sits near record lows and almost everything under construction is already spoken for. Enterprises and neoclouds that plan about two years out will find space. Late planners will pay more and wait longer.

Predictions are a risky sport, so we kept score. Each call below starts with what buyers and the market commonly expect, then gets tested against 2025 and 2026 data from brokers, earnings calls, regulators and the Federal Reserve. Some of those expectations held up. A few needed an edit. One needed a stern talking to. Figures are current as of November 2026.

# 2027 prediction Confidence Main signal
1 Capacity stays tight all year High JLL says 95% of the pipeline is precommitted and vacancy stays near zero through 2028
2 Hyperscalers and neoclouds keep taking the big blocks while smaller buyers queue High Hyperscalers, neoclouds and AI labs make up 77% of 2026 tenant demand in JLL data
3 Enterprises keep refreshing traditional servers and storage at higher prices High Dell traditional server and networking revenue up 235% and storage up 24%
4 Hardware costs level off late in 2027 at a high plateau, with storage easing first Medium TrendForce sees NAND prices falling from Q1 and DRAM increases leveling off in H2
5 More enterprise AI reaches production, mostly inference Medium to high HPE says enterprise AI orders more than doubled
6 Regulatory scrutiny of NVIDIA is a distraction, not a brake, and AMD scrutiny is thinner than headlines suggest Medium DOJ, SEC, China and EU reviews of NVIDIA, with no formal AMD probe found
7 AI spending growth cools at the edges, and neoclouds feel it first Medium A September rate hike, a 10-year yield near 4.9% and lenders pulling back
8 AI rules get louder in 2027 but not settled Medium Democrats take Congress in January and EU high-risk rules start December 2, 2027
9 Moratoriums and power rules change where and when sites get built more than how much High New York's 50 MW pause, county moratoriums and new large-load tariffs

Will capacity stay tight as data center growth keeps running?

Yes, and we think this is the easiest call on the list. JLL's North America Data Center Report Midyear 2026 puts vacancy at 1% for a third straight year. It says 95% of the development pipeline is precommitted, most tenants signing today are contracting for 2028 deliveries and vacancy is likely to stay near zero through 2028.

CBRE's H1 2026 report found primary market vacancy at a record low 1.4%, even after supply jumped 33.7% in a year. Preleasing covers 80.4% of capacity under construction, and less than 1,500 MW of future capacity is still available. That is about six months of demand. Cushman & Wakefield counts 37.7 GW under construction across the Americas, 91.7% of it precommitted.

So data center growth is real. It just arrives already sold. We expect 2027 to look like 2026 with a longer line.

Who gets the big blocks of capacity in 2027?

The usual suspects. Most data center growth goes to buyers who show up with the biggest commitments. JLL's 2026 tenant mix shows hyperscalers at 59% of demand, neoclouds at 11% and AI pure-plays at 7%. When those groups want 50 or 100 MW, operators listen.

Everyone else gets the scraps, and the scraps are small. JLL notes that enterprise requirements of 500 kW to 3 MW are struggling to find capacity too. CBRE says it is hard to find 5 to 10 MW of contiguous space in Northern Virginia, where vacancy is 0.24%. In Chicago, CBRE says no contiguous block of 5 MW or more frees up in 2026, and large blocks arrive in late 2027 at the earliest.

We do see one quiet bright spot. CBRE's Atlanta chapter says several operators are reserving capacity for enterprise customers to diversify their tenant base. That door is open, but it is not wide.

Will enterprises keep buying traditional infrastructure?

They will, and there's strong evidence they are already paying up to do it. The market commonly sees enterprises refreshing core servers and storage on schedule even as prices climb. The earnings back that up.

Dell's third quarter fiscal 2027 results, reported November 24, 2026, show traditional server and networking revenue of $15.0 billion, up 235%, and storage revenue of $4.9 billion, up 24%. COO Jeff Clarke told analysts he does not know of a server customer sitting on the sidelines. He also said the installed base of traditional servers is at an all-time high for age.

HPE's fiscal third quarter, reported September 2, 2026, showed server revenue up 35%. HPE said higher average selling prices in traditional servers offset unit volumes held back by supply. In plain English, buyers got fewer boxes for more money and bought them anyway. Refresh cycles are the unglamorous part of data center growth, and they are not going anywhere.

Do hardware and storage costs finally flatten in 2027?

Partly. We think the rate of increase slows in 2027, but prices land on a high plateau rather than sliding back. Storage looks set to ease before server memory does.

What Dell and HPE are saying

Clarke was blunt on Dell's November call. He said nothing in Dell's supply outlook suggests price declines in enterprise NAND and DRAM for servers, and that the crunch continues clearly into 2027. He did expect the rate of increase to slow, adding that a smaller percentage on a large number is still a lot of dollars. HPE CEO Antonio Neri said in September that DDR5, DDR4 and NAND had been constrained since early 2026, with some relief possible in 2027 as clean room capacity grows.

What the memory market is saying

TrendForce said on November 19, 2026 that NAND contract prices should fall 0% to 5% in the first quarter of 2027, with every category moving into a downward price cycle from the second quarter. Its November 25 update expects DRAM to stay tight through 2027, with quarterly increases narrowing and possibly leveling off in the second half.

In our opinion, flattening is a fair call for late 2027, especially for storage. Cheap servers are not. Budget 2027 refreshes at 2026 prices or a bit higher, and treat any discount as a nice surprise.

Does enterprise AI move from pilot to production?

Yes, though what we see is a steady walk rather than a sprint. Deloitte's 2026 State of AI in the Enterprise survey found only 25% of organizations had moved 40% or more of their AI pilots into production, while 54% expected to get there within three to six months. Gartner said in September 2026 that just 22% of organizations had scaled AI across multiple business units.

The vendors see buyers moving. HPE said enterprise AI orders more than doubled in its fiscal third quarter and described customers moving from pilots to production, often on traditional servers for inference and agentic work. Dell now counts more than 7,500 AI Factory customers.

For colocation, we see that kind of data center growth pointing to inference racks of modest size near users and data, rather than giant training halls. Those deployments still need dense power and often liquid cooling. Our liquid cooling guide covers what to ask.

Will regulatory scrutiny of NVIDIA and AMD slow data center growth?

We think probably not by much, though it makes 2027 noisier. As of November 2026, NVIDIA faces several regulatory reviews.

  • U.S. Department of Justice. An antitrust investigation covering NVIDIA's acquisitions, investments and sales practices, including its pending deal for Hugging Face, Reuters reported.
  • U.S. Securities and Exchange Commission. An inquiry into NVIDIA's accounting practices, Reuters reported on November 20, citing people briefed on the matter.
  • China's market regulator. A preliminary finding in September 2025 that NVIDIA violated conditions tied to its Mellanox purchase, with further investigation under way.
  • European Commission. An informal antitrust review of NVIDIA's market conduct.
  • Congress. Senate and House sessions with NVIDIA leadership set for early December.

Add a November CEO exit and return, and the distraction case is strong. NVIDIA still reported $107.6 billion in data center revenue for the quarter, up 110%. Chip supply, power and capital matter far more to your 2027 delivery date than any of these reviews.

AMD is where the evidence pushes back. We found no formal antitrust investigation of AMD in 2025 or 2026. A November short-seller report on AMD's China ties raised the prospect of more U.S. scrutiny, and AMD shares fell 8% that day. That is a risk to watch, not an open probe.

Does the AI trade slow data center growth in 2027?

Somewhat. In our view, chip demand stays strong, but the money behind it is getting more expensive and more choosy.

Are interest rates rising?

Yes. The Federal Reserve raised its target range a quarter point to 3.75% to 4% on September 16, 2026, then held in October. Minutes from that meeting say almost all participants expected further increases to be appropriate. The 10-year Treasury yield closed at 4.91% on November 24 and briefly topped 5% in mid-November. Rising rates are not a theory this time.

Will hyperscalers and neoclouds blink?

What we see is that hyperscalers blink a little and neoclouds blink harder. Microsoft trimmed its capex forecast for the year from $175 billion to $170 billion, and its CFO said delays at outside GPU suppliers push some capacity into the first half of 2027. Alphabet held at $195 billion to $205 billion. Amazon kept 2026 at $220 billion and said it would spend meaningfully more in 2027.

Credit is where the slowdown shows. Reuters reported in November that some banks are reluctant to fund more AI deals, even ones with guarantees from big technology names. J.P. Morgan Asset Management counts nearly $600 billion of AI-related debt issued in 2026 and says capital is still available but more expensive and more conditional. NVIDIA's then-interim CEO said the company will be far more selective about future financing deals, which feeds the circular financing debate. Gartner told CNBC it expects 80% of neocloud companies to be absorbed or shut down by 2030.

Our read is that spending keeps growing in 2027 but at a slower clip, and weaker borrowers get squeezed. If you are vetting GPU partners, our top neocloud companies list is a good place to start.

How much AI regulation is coming in 2027?

More talk, more hearings and a few real deadlines. Democrats take control of the House and Senate in January 2027, and Reuters reports they plan bills on independent testing of advanced AI and on shielding consumers from data center power costs. Passing them past a presidential veto is a different story.

At the state level, Colorado delayed and narrowed its AI law, which now takes effect January 1, 2027. A December 2025 executive order pushes for a single federal framework that would override conflicting state AI rules, but it does not propose preempting state rules on data center infrastructure. In Europe, the AI Omnibus pushed high-risk AI obligations to December 2, 2027.

For buyers, we think that means more compliance questions about where AI workloads run and who audits them, not a hard stop on data center growth.

Will moratoriums slow data center growth in 2027?

There's strong evidence they slow the large, new and power-hungry projects, and they push others to new places. New York's Executive Order 62, signed July 14, 2026, holds state permits for data centers of 50 MW or more while the state studies impacts. The order notes nearly 12 GW of data center load requests in the state's grid queue.

Counties are moving too. Manatee County, Florida approved a 12-month moratorium on new data center applications in October 2026, and Clackamas County, Oregon adopted a 120-day pause the same month. Data Center Watch counted at least 75 projects worth about $130 billion blocked or delayed in the first quarter of 2026 and another 45 worth nearly $68 billion in the second.

Power rules bite as well. Virginia regulators approved a Dominion rate class for large loads. New contracts signed from January 1, 2027 must run at least 14 years, and large customers pay at least 85% of their grid delivery costs whether they use the power or not. J.P. Morgan Asset Management expects post-election policy changes to shift when and where data centers get built more than how much demand exists.

What does data center growth in 2027 mean for colocation buyers?

In our view, the calendar is your biggest cost lever. Here is how buyers commonly see 2027 shaping up.

  • Lead times. For anything above a few megawatts, think 2028 delivery. Smaller retail deployments still move faster in markets with ready space.
  • Pricing. JLL says rents have risen about 9% a year since 2020, and most leases carry 3% or higher annual escalators with no concessions. Plan for that to continue.
  • Term lengths. Longer terms buy priority. Our wholesale colocation guide covers how terms shift by deal size.
  • Secondary markets. Power is moving deals to newer markets. Check carrier density before you fall for a cheap kilowatt.
  • Credit. Operators favor tenants with strong credit, so expect deposits or guarantees if you are a young neocloud.

What questions should colocation buyers ask about data center growth?

  • Is the capacity energized today, and if not, what utility agreement backs the ready-for-service date?
  • Is the site or its expansion exposed to a local moratorium or a pending state permit review?
  • What annual escalator applies, and is it capped?
  • Does a large-load tariff or minimum charge pass through to my bill?
  • Can I reserve expansion space now, and what does that option cost?
  • Can the hall support liquid cooling for future AI racks without a long retrofit?

Data center growth checklist for 2027 buyers

  • Map 24 months of power needs by quarter, including AI inference.
  • Lock 2027 hardware budgets at current prices.
  • Shortlist operators who can prove power, not just promise it.
  • Check each market for moratoriums, permit pauses and large-load tariffs.
  • Prepare credit support documents before the first call.
  • Compare at least one secondary market against your first choice.
  • Read our guide to choosing a colocation provider, then get quotes to compare options.

Frequently asked questions about data center growth in 2027

Will data center growth slow in 2027?

Demand will not slow much, but delivered capacity is capped by power, permits and financing. Expect fewer surprise openings and more preleased space.

Will colocation prices go down in 2027?

We think that's unlikely. With vacancy near record lows and escalators of 3% or more common, prices are more likely to rise or hold than fall.

Are interest rates going up or down for data center financing?

Up. The Fed raised rates in September 2026 and signaled more increases, and the 10-year Treasury yield sits near 4.9%.

Should enterprises sign longer colocation terms now?

If you know you will need the space, a longer term can lock capacity and price. Weigh that against flexibility and your growth plans.

Are data center moratoriums spreading?

Yes. New York paused state permits for large sites, and counties in Florida, Oregon and elsewhere adopted temporary pauses in 2026.

Do NVIDIA investigations affect GPU availability?

Not directly so far. Supply, power and financing drive GPU delivery dates far more than the current regulatory reviews.

More in Data Center Market Trends and Analysis

Compare facilities: All data center markets

Related

Comparing data centers?

Send us your requirements. We'll shortlist the providers that fit and get you pricing.