AI and High-Density Colocation Checklist (Free PDF)

GPU clusters break the assumptions most colocation was built on. Rack-scale systems draw around 120 kW per rack, need liquid cooling and weigh well over a ton. This checklist covers the 32 things to verify before you sign, from power ramps to CDU ownership.

Last verified November 22, 2026

Download the PDF PDF · 3 pages · free, no email required

What's in the AI and high-density colocation checklist

  • 32 checks in six areas: power and ramp, liquid cooling, building and structure, network, operations and contract terms
  • A why-it-matters note for every check
  • Liquid cooling questions on CDUs, facility water, secondary loops, leak detection and commissioning
  • Contract items for ramp dates, remedies, responsibility matrices and liquid cooling SLAs

What makes AI colocation different

Three things change at once. Power per rack rises by an order of magnitude, so the question is no longer how many cabinets you need but whether a hall can deliver 50, 100 or more kW to each one. Heat moves from air to liquid, which brings facility water, coolant distribution units and secondary loops into the deal. And racks arrive fully built and heavy, so floors, docks, doors and elevators become part of the evaluation.

Power that exists, on a schedule you can enforce

In AI deployments the most common delay is power that does not exist yet. Ask what is energized today, and for anything planned, ask for the signed utility agreement and an energization date. Then match a ramp schedule to your GPU deliveries, with ready-for-service dates in the contract and remedies if they slip. Without remedies, a missed date costs only you.

Liquid cooling questions that matter

Ask to see liquid cooling running for another customer. Then pin down ownership: who supplies, maintains and monitors the CDUs, who owns the secondary loop and its water quality, and who is liable if something leaks. Confirm the facility water supply temperature and flow per rack against your hardware vendor's requirements, using ASHRAE's liquid cooling classes, which run from W17 to W45. And insist on commissioning with your actual hardware before go-live.

Weight, delivery and the back-end fabric

A fully loaded rack-scale GPU system can exceed 3,000 pounds. Check the floor rating and every step of the delivery path for an integrated rack. Then plan the network: GPU clusters run a separate high-bandwidth fabric between racks, often with many fiber runs per rack and distance limits that depend on the cables and optics you choose. Keeping the cluster's rows together matters.

Contract terms for high-density deals

Standard colocation SLAs were written for air-cooled racks. Add commitments for liquid cooling: supply temperature, flow and response times. Put a responsibility matrix in the contract covering power, cooling, CDUs, manifolds, hoses and fittings. Secure expansion rights for the next block of power, and match the term to the useful life of the hardware rather than the provider's preferred deal length.

Red flags in AI and high-density colocation

Planned, not energized

Power on a utility queue with no signed date.

Liquid cooling on request

No live deployment you can see.

Nobody owns the CDU

Outages become disputes over responsibility.

Air-only SLA

No commitment on coolant temperature or flow.

No ramp remedies

Missed dates cost only you.

Path cannot fit the rack

Integrated racks cannot be taken apart for a small door.

The PDF covers each of these in full.

About this AI and high-density colocation checklist

Most colocation space was designed for air-cooled racks in the single digits of kW. Around 20 kW per rack, conventional air cooling reaches its practical limit, and NVIDIA rates its GB200 NVL72 rack-scale system at about 120 kW per rack with liquid cooling required. The gap between what a facility was built for and what GPU hardware needs is where AI deployments get delayed or go wrong.

We built this checklist for neoclouds, AI labs and enterprises deploying GPU clusters in colocation. It focuses on what is different from a standard deployment: power that exists today and on a contractual ramp, liquid cooling that is live rather than planned, structure and delivery paths for heavy integrated racks, the back-end GPU fabric, and contract terms that assign every cooling component an owner.

How to use the AI and high-density colocation checklist

  1. Download the PDF and send the checklist to each provider on your shortlist.
  2. Tick each item only when you have evidence: documents, a live deployment or a site visit.
  3. Treat anything you cannot tick as a question for the provider or a risk to price into the deal.
  4. Score the full facility with our data center checklist, and size power with the rack planner.

A planning checklist. Confirm every figure with the provider and your hardware vendor's site requirements.

Common questions

How much power does an AI rack need?

It depends on the hardware. Rack-scale GPU systems such as NVIDIA's GB200 NVL72 are rated at about 120 kW per rack, while air-cooled GPU servers in standard racks draw much less per rack but still far more than typical enterprise gear.

Do AI racks need liquid cooling?

Above about 20 kW per rack, conventional air cooling reaches its practical limit. Rack-scale GPU systems at around 120 kW per rack require liquid cooling.

What is a CDU?

A coolant distribution unit moves heat from the liquid loop that runs through your servers to the facility's water system, and controls temperature, flow and pressure. Who owns and maintains it should be written into the contract.

What should I ask a colocation provider about liquid cooling?

Whether it is running today for another customer, which types are supported, who owns the CDUs and secondary loop, the facility water temperature and flow per rack, leak detection and liability, and whether commissioning will be done with your hardware.

How heavy is a GPU rack?

A fully loaded rack-scale GPU system can exceed 3,000 pounds, so check floor ratings and the whole delivery path.